Accelerated gate one – the final decisions were published on 28 January 2021
Published date | Representation period closes | |
Submissions to RAPID | 28 September 2020 | |
Draft decisions | 1 December 2020 | 31 December 2020 |
Final decisions | 28 January 2021 |
Gate one – the final decisions were published on 8 December and 5 January 2022
Published date | Representation period closes | |
Submissions to RAPID | 5 July 2021 | |
Draft decisions | 14 September 2021 | 29 October 2021 (SESRO only – 19 November 2021) |
Final decisions | 8 December 2021 (SESRO only – 5 January 2022) |
Accelerated gate two – the final decisions were published on 17 May 2022
Published date | Representation period closes | |
Submissions to RAPID | 6 December 2021 | |
Draft decisions | 1 March 2022 | 12 April 2022 |
Final decisions | 17 May 2022 |
Gate two (excluding Cheddar 2 and Poole effluent reuse and transfers)
Published date | Representation period closes | |
Submissions to RAPID | 14 November 2022 | |
Draft decisions | 30 March 2023 | 11 May 2023 |
Final decisions | 28 June 2023 |
Gate two – Cheddar 2 and Poole effluent reuse and transfers only
Published date | Representation period closes | |
Submissions to RAPID | 14 November 2022 | |
Draft decisions | 10 May 2023 | 21 June 2023 |
Final decisions | 28 July 2023 |
Gate two – Mendips Quarries
Published date | Representation period closes | |
Submissions to RAPID | 17 July 2023 | |
Draft decisions | 11 December 2023 | 18 January 2024 |
Final decisions | 22 February 2024 |
Gate two – Upper Derwent Valley Reservoir Expansion
Published date | Representation period closes | |
Submissions to RAPID | 2025 timetable to be confirmed |